Day 1 : Arrival at Cádiz
The Island Sapphire arrived at our Cádiz facilities as a standard DP2 Platform Supply Vessel, featuring a 90-person accommodation, large clear deck, and reliable offshore supply configuration.
A solid platform ready to be transformed into a high-spec IMR and Walk-to-Work vessel capable of supporting subsea and maintenance operations.

Mid-Conversion – Helideck Installation
During this stage, major structural works were executed, including the installation of a 22m Helideck, the foundation for a 160 T lattice-boom crane, and the expansion of accommodation to 202 POB.
Each system was integrated under tight schedule and supervision, marking the core phase of the vessel’s 105-day evolution.

Day 105 : Project Completed
After only 105 days, the Island Sapphire was delivered as a fully upgraded IMR & W2W vessel, now equipped with:
-
160 T lattice-boom crane
-
23.4 m motion-compensated gangway
-
S-92 certified helideck
-
Accommodation for 202 POB
A fast, disciplined conversion completed on time, on spec, and to the highest industry standards.
.jpeg)
ATHENA II Phase 1: Arrival at Cádiz
The Athena II arrived at our Cádiz facilities as an IMR vessel prepared for a full transformation into a modern Walk-to-Work unit, marking the start of a fast-track conversion program.

ATHENA II – Phase 2: Crane Removal
Removal of the 64 T offshore crane to clear deck space and prepare foundations for the upcoming Ampelmann E-type gangway system.

ATHENA II – Phase 3: Crane at Yard
The original crane safely landed at the shipyard — detailed inspection and dismantling works carried out as part of the structural modification phase.

REDEFINING THE OFFSHORE INDUSTRY
ABOUT US
Green Parrot Marine (GPM) was established in May 2025 through the alliance of Blue Parrot Offshore and Verde Maritime.
GPM is Headquartered in Singapore.
We have management hubs in Madrid, Cadiz, and Mexico City.
We own and operate vessels designed to render services to the Offshore Oil & Gas and Renewable Energy sectors .

FROM PSV TO IMR IN 3 MONTHS
DAY 1
DAY 105

ATHENA II – Phase 4: Gangway Installation
Integration of the Ampelmann E-type motion-compensated gangway, ensuring full W2W capability and offshore compliance for future operations.

ATHENA II – Phase 5: Repainting & Rebranding
Complete repainting and rebranding under Green Parrot Marine’s identity — fresh livery, updated markings, and final outfitting ahead of delivery.

ATHENA II – Phase 6: Delivery to PRIO
The Athena II sails from Cádiz towards her charter with PRIO, now operating as a fully compliant W2W vessel, ready to begin her new offshore campaign.

FROM ACCOMODATION TO WALK TO WORK
FLEET
OUR CLIENTS

CONTACT
OUR PARTNERS


CORPORATE OFFICE SINGAPORE
72 Circular Road, #02-01, Singapore, 049426
EUROPE (CADIZ)
Chile Street, Polígono La Cabezuela, Parcela T5–T6, 11519 Puerto Real, Cadiz,
AMERICAS (MEXICO CITY)
Montes Urales 530 - 3, Office 301, Col. Lomas de Chapultepec, Alcaldia Miguel Hidalgo, Mexico City, C.P. 11000.